Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
A report which provided an update om the progress with the installation of solar photovoltaic panels at a number of Argyll and Bute Schools was considered. The report also provided recommendations on the way forward.
Decision
The Council noted -
1.
The
excellent progress with the solar pv installations at
the non NPDO schools and that the final installation at Park Primary School
should be completed during the school holiday period in October 2014.
2.
That
the projected Full Business Case for the NPDO Schools indicates that prudential
borrowing capital funding of circa £943,273 is required for the 5no. NPDO solar
pv projects at Dunoon Grammar, Rothesay Joint Campus,
Hermitage Academy, Oban Primary Campus and Lochgilphead Joint Campus to proceed
to the implementation/delivery stage.
3.
That
the projected Full Business Case shows an aggregated simple payback period of
10 years for the 5no. NPDO solar pv projects which is
well within the 14 year payback limit accepted by Council on 26 June 2014.
4.
That
on conclusion of an NPDO contract variation, expected in early September 2014,
the Executive Director of Customer Services will be in a position to accept
tenders on behalf of the Council for the installation of solar photovoltaic
panels at the NPDO schools based on the previously agreed delegated authority.
5.
That
a further update paper will be presented to Council on completion of the project.
(Reference: Report by Executive Director – Customer Services
dated 27 August 2014, submitted)
Publication date: 01/10/2014
Date of decision: 25/09/2014
Decided at meeting: 25/09/2014 - Argyll and Bute Council