Decisions:

The Council considered a report advising that an operational issue with the adjustment to parking meters will result in a delay in implementing a decision by the Policy and Resources Committee on 21 August 2014.  The decision was to instruct officers to end the temporary suspension of parking charges in the Sinclair Street car park from 1 September 2014 to 31 December 2014, with the proviso that the first two hours be free to compensate for the loss of on-street parking during phases three and four of the CHORD works.

 

Decision

 

The Council –

 

1.        Noted the content of the report.

 

2.        Agreed to the new implementation date of 20 October 2014.

 

3.        Agreed to delegate determination of a suspension of car parking charges across Argyll and Bute during the Christmas period to the Policy and Resources Committee.

 

(Reference:  Report by Executive Director – Development and Infrastructure Services dated September 2014, submitted)

 

 

 

 

Publication date: 01/10/2014

Date of decision: 25/09/2014

Decided at meeting: 25/09/2014 - Argyll and Bute Council