Rothesay Flood Prevention Scheme


Construction of the Rothesay Flood Prevention Scheme began 15th September 2003.

Flooding has been a major problem in the sheltered bay of Rothesay for a number of years:

  • tidal surges can cause water to rise above the level of the esplanade
  • the frequency of flooding incidents is on the increase
  • 50 - 60 properties are affected by a major flooding incident
  • in 1991, between £3 and £4 million worth of damage caused to properties

Example of flooding in Feb' 2002
Example of flooding in Feb' 2002

This £1.75 million scheme is designed to protect Rothesay Town Centre against a 1 in 100 year flood event and involves the construction of a flood wall along the back of the esplanade between MacKinlay Street and Albert Pier.

Extents of new flood wall
Extent of new flood wall

The contract has been awarded to Raynesway Construction Services Ltd and is programmed to take 35 weeks to complete.

PROGRESS REPORT - August 2004

The flood prevention works are now nearing substantial completion with the majority of the flood walls complete.

Wall at Outer Harbour nearing completion
Wall at Outer Harbour nearing completion

A number of delays have been caused to the construction works mainly due to finding uncharted services which have had to be diverted clear of the works. There have also been problems with the supply of precast concrete copes to finish off the top of the walls.

The revised completion date is now early September 2004.

Esplanade being prepared for resurfacing
Esplanade being prepared for resurfacing

For several weeks, the contractor has had a workforce of 50 operatives on the site and is working until 8pm to ensure that no further delays occur.

The raised stacking area is now complete and the main part of the esplanade is being prepared for resurfacing. As sections of the wall are completed, these areas will be re-opened to the public.

Completed raised stacking lanes<BR>
Completed raised stacking lanes

PROGRESS REPORT - December 2004

The flood prevention scheme was substantially completed in mid-October with only minor works to fencing and parapets still to be completed. Here are some pictures of the completed project.

Rothesay Flood Prevention Scheme

Rothesay Flood Prevention Scheme

Rothesay Flood Prevention Scheme

Rothesay Flood Prevention Scheme

See also:
TURNING THE TIDE FOR ROTHESAY.
null.
ROTHESAY FLOOD PREVENTION SCHEME ON SITE.
Positive about Disabled People LogoInvestor in People Logo
Argyll and Bute Council, Kilmory, Lochgilphead, Argyll, PA31 8RT
Telephone: 01546 602127 Email: enquiries@argyll-bute.gov.uk
Argyll and Bute Council is not responsible for the content of external websites