| What needs to be done | Partners we need to work with | Indicative cost | Indicative Timescale |
| 2007 - 2010 | 2010 - 2015 | 2015 - 2025 |
| AT01. Develop and Cycling and Walking Strategy |
| Produce a Cycling and Walking Strategy for the area as a daughter document to the Local Transport Strategy. | - | - | red (complete by end 2008) | | |
| What needs to be done | Partners we need to work with | Indicative cost | Indicative Timescale |
| 2007 - 2010 | 2010 - 2015 | 2015 - 2025 |
| AT02. Develop and implement Travel Plans |
| Develop and implement a travel plan for Argyll and Bute Council. | | - | red (1) | green | |
| Support NHS in the development of travel plans for health facilities | | - | red (1) | green | |
| Encourage employers in the area to develop and implement travel plans. | - Local industry
- Public agencies
- Staff
| - | red (begin 2009) | green | |
| Continue to encourage schools to develop and implement travel plans and assist schools in putting in place those measures that "Tackle the School Run". | | - | green (complete by end 2008) | | |
| Promote car-sharing schemes. | - SPT
- Hitrans
- Scottish Executive
| - | red | green | |
| Promote video-conferencing | - Hitrans
- Scottish Executive
- HIE
| - | green | | |
[(1) - denotes Project Development 2007-08, Project Delivery to begin by 2008]
| What needs to be done | Partners we need to work with | Indicative cost | Indicative Timescale |
| 2007 - 2010 | 2010 - 2015 | 2015 - 2025 |
| AT03. Improve infrastructure for active travel. |
| Continue to investigate and support opportunities for local access arising from the Core Path Plan. | | - | red | red | red |
| Ensure the needs of pedestrians and cyclists are considered at the planning stage of developments to maximise opportunities for cycling and walking. | | - | red | red | red |
| Develop Oban - Fort William cycleway - part of the National Cycle Network. | - Hitrans
- Sustrans
- Neighbouring authorities
| £4 million | red (1) | green | |
| A815 Hafton / Ardnadam footway - provision of missing footway link | | £500,000 | green (1) | | |
| Dumbarton - Helensburgh cycleway - completion of final section.* | - SPT
- Sustrans
- LLTNP
- Neighbouring authorities
| £400,000 | red | green | |
| Investigate options for cycle route between Loch Lomond and National Cycle Network in West Argyll. (e.g. Tarbert / Arrochar / Inveraray.) | - SPT
- Sustrans
- LLTNP
- Neighbouring authorities
| £50,000 | red (1) | green (complete by end 2012) | |
| Investigate options for tourism cycling on our islands. | - Scottish Executive
- Sustrans
| £20,000£50,000 | green (1) | | |
[(1) - denotes Project Development 2007-08, Project Delivery to begin by 2008]
| What needs to be done | Partners we need to work with | Indicative cost | Indicative Timescale |
| 2007 - 2010 | 2010 - 2015 | 2015 - 2025 |
| AT04. Promote benefits of active travel. |
| Publicise the benefits of active travel, e.g. information pages on the Council website, promotional campaigns including initiatives such as Walk to Work Week, etc.. | | - | green | | |